How much time does a permit allow me to build?
Every permit issued shall become invalid unless the work authorized by such permit is commenced within 180 days after its issuance, or if the work authorized by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing and justifiable cause demonstrated.

Show All Answers

1. When do I need a building permit?
2. Are there regulations for living in a Recreational Vehicle (RV)?
3. When am I Exempt from a Permit?
4. How much time does a permit allow me to build?
5. How long does it take to issue a permit?
6. When do I schedule an inspection?
7. Do agricultural buildings require a permit?